Project SEK002383 (Pacific Park Project Phase II) – Department of Design and Construction (DDC)

Purpose

The purpose of the project is to (1) upgrade sewer sizes to provide residents in the newly constructed buildings with sufficient capacity for sanitary discharge and to convey storm water from the area, (2) to install new distribution water mains to help with peak demands, (3) to improve the sizing of distribution water mains, and (4) to improve fire protection in the area.

Locations

The project location/scope is (1) a new 48″ combined sewer in Dean St. between 6th Avenue and Vanderbilt Avenue, and Vanderbilt Avenue between Dean Street and Pacific Street, (2) new 8″, 12″, and 20″ distribution water mains in Dean Street between Carlton Avenue and Vanderbilt Avenue, Vanderbilt Avenue between Dean Street and Atlantic Avenue, and Carlton Avenue between Dean Street and Pacific Street.