Attached please find Five (5) Community Advisory Notice for Brooklyn
Community Advisory Date: Monday – 8/18/2025
Work date: Monday- 8/25/2025
Operation: Work to be performed but is not limited to:
Mobilization of Equipment , Saw Cutting of
Roadway, Tree Pruning and Tree Guards
Time: 7:00am to 6:00 pm
Locations:
St. John’s Ave between Franklin Ave and New York Ave
Sterling Place between Franklin Ave and New York Ave
Bedford Ave between Lincoln Pl and Park Pl
Rogers Ave between Prospect Pl and Lincoln Pl
Nostrand Ave between Prospect Pl and Lincoln Pl
Please abide by the “NO PARKING” signs as contractor equipment needs to access the area.
Driveway access may be limited during construction times.
A 24 hour contractor notice will be posted on your door prior to all water service interruptions.
—
Please feel free to reach out to me via email or phone if you have any questions or concerns about the project.
I am here to assist you through this process.
Best,
Nicole Chati
Community Construction Liaison
Techno Engineers
Project RED395AC~Replacement of Distribution Water Main in Various Locations.
Cell:609-608-2651
Field Office:718-887-2373
Field Office: 201 Arlington Avenue, Staten Island, NY 10303 Suite 2D
RED395AC START UP NOSTRAND AVE 8 25 2025
RED395AC START UP ROGERS AVE 8 25 2025
RED395AC START UP STERLING PL 8 25 2025