This letter is to notify you of a utility job that has been scheduled to begin approx. 1/05/2022. The location is Nostrand Avenue (see attached diagram). The working hours determined by NYCDOT Permit office. The work should be completed in 4 weeks depending on weather.

Scope of work

  1. Excavation and installation of 1-4” PVC fiber optic conduits in the street and sidewalk

          (Approx. 310 LF).

2)  Install new 30” x 48” x 36” hand hole in sidewalk –1 EA

3)  Backfill and full street and sidewalk restoration.

click here;  Permit Diagram

If you have any questions or need additional information, please feel free to call me at 718-994-3111, ext. 116.