Please see attached bulletin for this week’s work.
Work schedule for 3/14/2022 – 3/18/2022:
- Intersection of Sterling Place and Vanderbilt Avenue: Installation of catch basin chutes
- Intersection of Park Place and Vanderbilt Avenue: Installation of catch basin chutes
- Intersection of Carleton Avenue and Park Place: Installation of utility wingbacks at sewer chamber