Please see attached bulletin for next week’s work.
Work schedule for 4/04/2022 – 4/08/2022:
- Intersection of Sterling Place and Vanderbilt Avenue: Installation of catch basin chutes and utility wingbacks
- Intersection of Park Place and Vanderbilt Avenue: Installation of catch basin chutes and utility wingbacks
- Intersection of Carleton Avenue and Park Place: Forming sewer chamber, setting rebar, and pouring base slab
Click Here: Park Place-Weekly look-ahead bulletin-4-04-22
Best,
Danilo Mikhaylov – Community Construction Liaison (CCL)
NYC Department of Design and Construction