Please see attached bulletin for next week’s work. 

Work schedule for 4/04/2022 – 4/08/2022:

  • Intersection of Sterling Place and Vanderbilt Avenue: Installation of catch basin chutes and utility wingbacks
  • Intersection of Park Place and Vanderbilt Avenue: Installation of catch basin chutes and utility wingbacks
  • Intersection of Carleton Avenue and Park Place: Forming sewer chamber, setting rebar, and pouring base slab

Click Here:  Park Place-Weekly look-ahead bulletin-4-04-22

Best,

Danilo Mikhaylov – Community Construction Liaison (CCL)

NYC Department of Design and Construction

Project # SEK002386