Please see attached weekly bulletin for next week’s construction activities. 

Work schedule for 3/07/2022 – 3/11/2022:

  • Intersection of Sterling Place and Vanderbilt Avenue: Installation of catch basin chutes
  • Intersection of Park Place and Vanderbilt Avenue: Installation of catch basin chutes
  • Intersection of Carleton Avenue and Park Place: Installation of Sewer Chamber Utility Wingbacks

Click here for more info: ParkPlace-Weekly look-ahead bulletin-3-07-22