Weeks of
In an effort to keep the Atlantic Yards Community aware
of upcoming construction activities, ESD and Forest City Ratner
provide the following outline of anticipated upcoming construction activities.
Please note: the scope and nature of activities are
subject to change based upon field conditions.
All work has been approved by appropriate City and State
agencies where required. In addition to the activities described below noise
attenuation and vibration monitoring measures are underway in connection with
the Memorandum of Environmental Commitments dated
If you have any
questions please feel free to contact our project Ombudsperson at: 212-803-3233
or AtlanticYards@empire.state.ny.us
Long Island
Rail Road/Vanderbilt Yard Work
• Continue excavation, testing tie-backs and installation of 2nd tier/cross lot
bracing in Southeast Gas Station (block 1121, lot 47).
• Continue construction and debris removal from block 1121.
• Continue hauling soil from block 1121.
• Continue north foundation for cable bridge.
• Continue south foundation for cable bridge.
• Installation of temporary access ramp structure.
• Drill coffer dam piles at
• Prep west abutment of trestle for concrete placement.
• Continue drilling trestle piles.
Abatement and Demolition Work
All work described below will comply with the additional
oversight and protocols by the Department of Buildings (DOB) that were
established on
• Demolition is
underway at
continue throughout this two week period.
• Demolition is complete at
• Demolition is complete at
• Demolition will begin at
two week period.
• Demolition will resume at
week period.
Utility Work
All utility work scheduled to take place in Flatbush
Avenue will only take place at night (between 10PM and 6AM) as mandated by DOT.
• The first of three phases of upgraded water and sewer installations is
underway and is expected to continue through the end of the year. Work will
continue on
between Pacific and Dean Streets. Night time work began on
sewer chamber on
• Transit ducts on
be relocated. This work is expected to continue over the next three months.
All work taking place in the sidewalk will occur during the day. Pedestrian
walkways will be maintained.
Private Utility Work
The work described below is managed and contracted by the
respective private utility companies, as indicated.
• ConEd will be installing
conduits on Dean between Flatbush and 6th Avenues and
working on a feeder at
• Verizon will be splicing
cable on
Avenues and at
• Time Warner Cable and Keyspan
will be working at
Avenues.