EASTERN PARKWAY RECONSTRUCTION PROJECT
RECONSTRUCTION OF EASTERN PARKWAY WASHINGTON AVENUE TO GRAND ARMY PLAZA
Project ID#: HWKC1019
Work Continues For Eastern Parkway Project
The NYC Dept. of Design and Construction's (DDC) continues work for the Eastern Parkway Reconstruction project from Washington Avenue to Grand Army Plaza. The project is scheduled for completion in the Fall of 2012. There are several work operations associated with this project, among them are:
Installation of trunk and distribution water mains, combined
sewer replacement, and its components.
Installation of new pavement, curbs and sidewalks, catch
basins, chute connections, ADA compliant pedestrian ramps,
manholes, fire hydrants, street lighting and traffic signals.
Reconstruction of the median.
Work Scheduled:
Eastern Parkway from Underhill Avenue to Washington Avenue:
Continue installation of the 15" combined sewer.
Installation of the trunk water main.
The following is the anticipated construction work schedule, field conditions permitting
for next week. Please note that parking may be restricted in work area.
Date Location Operation Work Hours
4/30/12
Eastern Parkway (Main Roadway) between Washington Avenue and Brooklyn Museum's driveway
Intersection of Eastern Parkway and Flatbush Avenue
Excavation for Roadbase Installation
Curb Installation
7:00AM - 6:00PM
5/1/12
Eastern Parkway (Main Roadway) between Washington Avenue and Brooklyn Museum's driveway
Intersection of Eastern Parkway and Flatbush Avenue
Excavation for Roadbase Installation
Curb Installation
7:00AM - 6:00PM
5/2/12
Eastern Parkway (Main Roadway) between Washington Avenue and Brooklyn Museum's driveway
Intersection of Eastern Parkway and Flatbush Avenue
Excavation for Roadbase Installation
Curb Installation
7:00AM - 6:00PM
5/3/12
Eastern Parkway (Main Roadway) between Washington Avenue and Brooklyn Museum's driveway
Intersection of Eastern Parkway and Flatbush Avenue
Excavation for Roadbase Installation
Curb Installation
7:00AM - 6:00PM
5/4/12
Eastern Parkway (Main Roadway) between Washington Avenue and Brooklyn Museum's driveway
Intersection of Eastern Parkway and Flatbush Avenue
Excavation for Roadbase Installation
Curb Installation
7:00AM - 6:00PM
NOTES:
PARKING ELIMINATED ALONG:
o Eastern Parkway Main Roadway (North & South Curb Lanes) between Washington Avenue and Grand Army Plaza.
In effect since 6:00am on Thursday, March 22, 2012 for approximately two (2) months / 24 hours a day.
o Eastern Parkway (Service Roadway) between Plaza Street East and Underhill Avenue (South Curb Lane Only). No Parking will be in effect 24 hours a day.
o Washington Avenue between Eastern Parkway and Union Street (East & West Curb Lanes). Approximately 200 linear feet measured from the Eastern Parkway corner. No Parking will be in effect 24 hours a day.
o Washington Avenue between Eastern Parkway and Lincoln Place (East & West Curb Lanes). Approximately 200 linear feet measured from the Eastern Parkway corner. No Parking will be in effect 24 hours a day.
PARKING PERMITTED ALONG:
o Eastern Parkway North Service Road (North Curb Lane Only, buildng side) from Plaza Street East to Underhill Avenue.
o Eastern Parkway North Service Road (North & South Curb Lanes) from Underhill Avenue to Washington Avenue.
Due to unforeseen conditions, it may become necessary to change some scheduled work locations and operations.
For further information, please call Scott Payne the Community Construction Liaison at 347-457-5362 or email: easternparkwayccl@gmail.com Website: www.nyc.gov/ddc Video: http://www.youtube.com/newyorkcityddc
*********
The NYC Dept. of Design and Construction (DDC) has commenced work on the Eastern Parkway Reconstruction project from Washington Avenue to Grand Army Plaza. The project is scheduled for completion in Fall 2012. This work is necessary to upgrade the existing NYC infrastructure to accommodate the growing demands of increased residential and business development.
The work operations associated with this project are:
*Installation of trunk and distribution water mains, combined sewer
replacement, and its components.
* Installation of new pavement, curbs and sidewalks, catch basins,
chute connections, ADA compliant pedestrian ramps, manholes, fire
hydrants, street
lighting and traffic signals
Community Impacts
The DDC is committed to maintaining a worksite that is safe and clean.
We realize that dust, noise, and heavy equipment are intrusive but
they are common elements of construction. We ask for your patience
during the project. During construction hours you can expect the following:
*Increased levels of noise.
* Some traffic lane changes, roadway closings, and delays.
*The typical work hours are from Monday through Friday, 7:00 am until
6:00 pm; weekend work may occur at times.
*Possible driveway and street parking restrictions (in order to proceed
safely). Signs will be posted in advance as required. Vehicles in
violation may be towed.
*Signs, advisories, and temporary construction barriers which will
guide traffic and pedestrians to promote safety.
* Dust, dirt, and mud typically associated with construction sites.
* Machines and materials stored, but cordoned, along the streets nearby
or within the project limits.
Property Damage
You are advised to inform the DDC or the Contractor of any property
damage that you may have. If the contractor fails to respond within
10 days, you should inform the DDC Borough Director in writing. If
you intend to file a claim you must do so within 90 days of the occurrence
with the New York City Comptroller’s Office.
Special Needs
Please let the Community Construction Liaison (CCL) know if there
is anyone in your household or building that has special needs so
that we can coordinate our construction activities accordingly.
Water Service Interruption
During the course of the project there will be water service interruptions
while old mains are removed and new mains installed. Advanced notice
will be given for all planned interruptions. If it is necessary for
us to turn off your water service, you will receive written notice
informing you by the afternoon of the day before the service interruption.
We suggest you store drinking water to have available in your home
or business for the period that the water service is suspended. Water
service is always restored at the end of the day. Be sure to turn
off any open valves or faucets to prevent flooding when water service
is restored. After water service is restored, the water may be discolored by sediment that has accumulated
in older pipes, including the service connection to the internal pipes
in your building. Even if no construction is preformed in front of
your building the process of shutting down old pipes can result in
discoloration. If this occurs, run only cold water until it appears
clear.
Newsletter Distribution:
Construction Newsletters will be distributed within the project area,
and at key locations including:
* Community Board Districts 8 and 9
*Brooklyn Public Library -- 1 Grand Army Plaza
Community Construction Liaison (CCL):
The DDC has assigned Scott Payne of Haks Engineers as the Community
Construction Liaison (CCL) for this project. Please contact Mr. Payne
for any project related inquiries/concerns you may have:
* Phone: (347) 457-5362 Fax: (347) 457-5364
* Email: easternparkwayccl@gmail.com
Field Office Address: 250 Flatbush Avenue, Brooklyn, NY 11217



